Hi,
I've got a task of 1 day's work that was originally planned with a duration of 5 days.
The resource has now told me that she will do the work on a single day, due to vacation days.
I added the vacation days into her calendar, fixed the given start and end dates, and changed the given duration to 1 day.
However, the planned duration is still showing 5 days, equating to over 28 edays, because of her planned vacation.
I can't seem to make the gantt chart show the new reality, which means all other dependant tasks are now pushed by 4 weeks.
The only way I can make it show the task just taking one day is to mark the task as complete.
Is there a better way?
Thanks!
Mark