Hi all!
I've been a proud user of Merlin Project for some months and I have a doubt with Merlin about which I have not found any information and it's driving me crazy.
The ACWP is well calculated separately (€20) but in the project the value I have is €10 because it's calculated progressively (I think). The logical thing would be that the top value should be €20 as well, not €10.
When the tasks are not parallelised everything is calculated as it should, but I don't know why in these cases the data is misleading because when I use the ACWP for any other metric such as Cv (as you can see it also gives incorrect values.
Would you be so kind as to bring me some light?
Thx!