ed Hi, this is not possible with Express.
In Merlin Project you can show the originally planned dates (Planned Start or Planned End) as column…

and as an additional gantt bar, enabling the Secondary bars in the View options

In addition… ever since v9 Merlin Project has a Dynamic baseline. Just select a Reference date in the past for the Planned values and the secondary bar to show as expected then.