gregh Hey there, About to use Merlin for construction work planning. Can't find help to do this: I want the work (task) duration do move with 1 day increments when moved and resized graphically. Is it possible? Thanks a lot!
vicky If the bottom Gantt chart unit is set to Weeks, and you move a bar on the Gantt, it will be moved to the starting point of the next day. You cannot resize a bar graphically in 1 day increments.
gregh Okay, thank you for your answer. having merlin work like it does with "week" units and displaying individual days would be perfect... a bit disappointing to be so close to it!