Macca I need to adjust my tasks so the lead/lag time is all days (working and non working)... 5 days give me only working days. I want include all days. This is particularly interesting in stability studies of products.
vicky Hi Macca, you can use the edays unit. 5 edays starting from Wednesday will include the weekend too.